| Task n# | Description | Assignee | Date | Status | Deadline | ||
A1-01 | Group representatives are asked to announce their needs regarding radioactive waste storage. S. Roesler (HSE-RP) will report on this subject in one of the upcoming LS3 committee. | ALL GROUPS | Initiated on 20-03-2024 LS3C#1 | CLOSED on 27.11.2024 | End of 2024 | ||
| R1-01 | LS3C participants to pass the message inside their group/department that the situation is critical in term of space needed for storage during LS3. A reasonable number in term of needed volume (without contingency) and a realistic timeline should be given to G. Riddone as soon as possible. | ALL GROUPS/DEPARTMENTS | Initiated on 20-03-2024 LS3C#1 | Ongoing | End of 2024 | ||
| A2-01 | The activities to be scheduled during the LS3 involved EN-EL for major (de)cabling (i.e. HL-LHC, NA-CONS, PSS-CONS) should be requested at latest on 30th of June 2024. For all other projects and works the deadline is set to 30th of September 2024 | ALL GROUPS/PROJECTS | Initiated on 17-04-2024 LS3C#2 | Ongoing | Need deadline extension | ||
| A2-02 | Equipment drawings shall be released – “Valid for Production” or “Valid for Installation” – at the end of the design study or upgrade. | DESIGN OFFICES | Initiated on 17-04-2024 LS3C#2 | Ongoing | Long term action | ||
| R2-01 | Relevant Projects and Groups must have representatives at the ICL Meetings | ALL GROUPS/PROJECTS | Initiated on 17-04-2024 LS3C#2 | Ongoing | Long term action | ||
| R2-02 | The need for transports of bulky and/or highly activated objects or activated items with exotic material composition (e.g. heavy metals) should be announced to RP and EN-HE as soon as possible | ALL GROUPS/PROJECTS | Initiated on 17-04-2024 LS3C#2 | Ongoing | – | ||
| A3-01 | To reach out to their RSO and inform RP regarding their planned interventions during LS3 before mid-June, to assess if any ALARA Level 3 committee will be necessary | ALL GROUPS/PROJECTS | Initiated on 15-05-2024 LS3C#3 | CLOSED | – | ||
| A4-01 | Report on declared ALARA3 level interventions within 6 weeks | ALL GROUPS/PROJECTS | Initiated on 29-05-2024 LS3C#4 | CLOSED (LS3C#7) | – | ||
| A5-01 | Report on the power consumption simulations of SM18 during the reduction of the available electrical power capacity during LS3 Status on 24/07/2024 by S. Machado: there is no simulation that has been made so far. In contact with L. Scibile to get an overview of the maintenance activities in SM18 and waiting for feedback. This action is ongoing. Action closed on 29/08/2024 following these conclusions:
| EN-EL | Initiated on 12-06-2024 LS3C#5 | CLOSED | – | ||
| R5-01 | Nominate a safety coordinator during the conception phase (part-time) | SRF Project | Initiated on 12-06-2024 LS3C#5 | CLOSED | – | ||
| A6-01 | Identify and communicate to the LS3 Scientific Secretary the name of the speaker for the LS3 Readiness Review in September | ALL GROUPS/PROJECTS | Initiated on 26-06-2024 LS3C#6 | CLOSED | – | ||
| A7-01 | Inform Marine Gourber-Pace in case of operation or early commissioning that require accelerator and/or industrial control systems during LS3 | Experiments | Initiated on 03-07-2024 LS3C#7 | Ongoing | Long term action | ||
| R7-01 | White Rabbit Central Timing components shall be tested by equipment owner before installation in particular before installation in SM18 and Linac4 | Equipement groups | Initiated on 03-07-2024 LS3C#7 | Ongoing | Long term action | ||
| R7-02 | Anticipate a potential need for procurement contract extensions in case of a shift of the start of LS3 | All Groups/Projects | Initiated on 03-07-2024 LS3C#7 | Ongoing | – | ||
| R7-03 | Announce all requests to SCE-SAM | All Groups/Projects | Initiated on 03-07-2024 LS3C#7 | Ongoing | – | ||
| A8-01 | To communicate the needs for additional dosimeters and training for LS3 to the RP service. S. Roesler (HSE-RP) will report on this subject in one of the upcoming LS3 | All Groups/Projects | Initiated on 24-07-2024 LS3C#8 | Ongoing | End June 2025 | ||
| A9-01 | To verify the respective 171 PLAN contribution for which EN-EL misses a ticket request as well as the 34 SNOW tickets classified as incomplete tickets by EN-EL | All Groups/Projects | Ongoing | – | |||
| R10-01 | Ensure proactive coordination and adapt schedule with service/equipment groups, facilities, and projects for interventions on the power network of critical and safety equipment during LS3 | EN/EL | Initiated on 21-08-2024 LS3C#10 | Ongoing | Integrated in EL quality plan | ||
| A10-01 | Communicate the impacts of the EN-EL consolidation activities on users and in particular experiments. | EN/EL and ALL | Initiated on 21-08-2024 LS3C#10 | CLOSED | Coordination meetings initiated | ||
| A10-02 | Review the invalidated PLAN contributions related to cable identification, as the YETS 2024-2025 is the final opportunity to address this. | All Groups/Projects | Initiated on 21-08-2024 LS3C#10 | Ongoing | – | ||
| A10-03 | Review and finalize the ECRs for YETS 2024-2025. | All Groups | Initiated on 21-08-2024 LS3C#10 | Ongoing | – | ||
| A10-04 | Review the ECRs for LS3 (i.e. check if anything is missing, incorrect, or incomplete). | All Groups | Initiated on 21-08-2024 LS3C#10 | Ongoing | – | ||
| A10-05 | Review the integration studies/ECRs list to keep it as up to date as possible. | All Groups/Projects | Initiated on 21-08-2024 LS3C#10 | Ongoing | – | ||
| A11-01 | Provide lists of pressure safety valves validations, AUG tests, smoke detection systems tests, and other critical safety systems that need periodical tests (scope YETS 2025-26) to LS3-scientific-secretary@cern.ch (then communicated to HSE) | All Groups | Initiated on 16-10-2024 LS3C#11 | Ongoing | End of 2024 | ||
| A12-01 | Finalization of Experimental Areas ECRs for YETS 2024-25 | All groups concerned | Initiated on 30-10-2024 LS3C#12 | Ongoing | – | ||
| A13-01 | Look at the list of facilities requesting to run during LS3 and the respective requested services (including EN-EL). Raise any concerns/issues by mid-January 2025 to B.Mikulec or via the LS3 Scientific Secretary | All groups/services | Initiated on 27-11-2024 LS3C#13 | Ongoing | Mid-January 2025 Deadline extended to end of March 2025 | ||
| A14-01 |
| Provide the name of the safety person(s) (if not part of the LS3C members already) to be invited to the safety-dedicated LS3 meeting that will be held in May 2025. | ALL groups/projects | Initiated on 19-02-2025 LS3C#14 | Ongoing | 31st of March 2025. | |
| Provide the name of the safety person(s) (if not part of the LS3C members already) to be invited to the safety-dedicated LS3 meeting that will be held in May 2025. | |||||||
| A14-02 | Provide or update the space request needs according to the new LS3 schedule. Inform if barracks/bungalows are provided by Contractors or by CERN. | ALL groups/projects | Initiated on 19-02-2025 LS3C#14 | Ongoing | 28th of February 2025 | ||
| A14-03 | Submit all requests related to IT cabling (DC-IT) for the LS3 by SNOW ticket before the 31st of March 2025 and create the corresponding PLAN contribution (link the SNOW ticket number). Late requests may be subject to long delays or declined. | ALL groups/projects | Initiated on 19-02-2025 LS3C#14 | Ongoing | 31st of March 2025 | ||
| A14-04 | Record in the RW forecast share-point any equipment presently stored in storage buildings that will be disposed as radioactive waste. | ALL groups/projects | Initiated on 19-02-2025 LS3C#14 | Ongoing | 30th of June 2025. |
Task numbering according to its character:
<character><sessionNo.>-<occurrence>
Character A : ACTION
Character R : RECOMMENDATION
Character D : DECISION