Task n#DescriptionAssigneeDateStatusDeadline

A1-01

Group representatives are asked to announce their needs regarding radioactive waste storage. S. Roesler (HSE-RP) will report on this subject in one of the upcoming LS3 committee.

ALL GROUPS

Initiated on 20-03-2024 LS3C#1

CLOSED

on 27.11.2024

End of 2024

R1-01LS3C participants to pass the message inside their group/department that the situation is critical in term of space needed for storage during LS3. A reasonable number in term of needed volume (without contingency) and a realistic timeline should be given to G. Riddone as soon as possible.ALL GROUPS/DEPARTMENTS

Initiated on 20-03-2024 LS3C#1

Ongoing

End of 2024
A2-01The activities to be scheduled during the LS3 involved EN-EL for major (de)cabling (i.e. HL-LHC, NA-CONS, PSS-CONS) should be requested at latest on 30th of June 2024. For all other projects and works the deadline is set to 30th of September 2024ALL GROUPS/PROJECTS

Initiated on 17-04-2024 LS3C#2

OngoingNeed deadline extension
A2-02Equipment drawings shall be released – “Valid for Production” or “Valid for Installation” – at the end of the design study or upgrade.DESIGN OFFICES

Initiated on 17-04-2024 LS3C#2

OngoingLong term action
R2-01Relevant Projects and Groups must have representatives at the ICL MeetingsALL GROUPS/PROJECTS

Initiated on 17-04-2024 LS3C#2

OngoingLong term action
R2-02The need for transports of bulky and/or highly activated objects or activated items with exotic material composition (e.g. heavy metals) should be announced to RP and EN-HE as soon as possibleALL GROUPS/PROJECTS

Initiated on 17-04-2024 LS3C#2

Ongoing–
A3-01To reach out to their RSO and inform RP regarding their planned interventions during LS3 before mid-June, to assess if any ALARA Level 3 committee will be necessaryALL GROUPS/PROJECTS

Initiated on 15-05-2024 LS3C#3

CLOSED–
A4-01Report on declared ALARA3 level interventions within 6 weeksALL GROUPS/PROJECTS

Initiated on 29-05-2024 LS3C#4

CLOSED

(LS3C#7)

–
A5-01

Report on the power consumption simulations of SM18 during the reduction of the available electrical power capacity during LS3

Status on 24/07/2024 by S. Machado: there is no simulation that has been made so far. In contact with L. Scibile to get an overview of the maintenance activities in SM18 and waiting for feedback. This action is ongoing.

Action closed on 29/08/2024 following these conclusions:

  • Considering the EL planning presented so far, along with the planning presented by Luigi, the only power limitation identified is during the EN-EL consolidation of SEM12 (approx. 4 months towards the end of LS3).
  • During this phase, the SM18 complex will be supplied via the backup cable from BA7 (power limited to 8 MVA).
  • The situation will be revisited in the future once the plans are more refined.
EN-EL

Initiated on 12-06-2024 LS3C#5

CLOSED–
R5-01Nominate a safety coordinator during the conception phase (part-time)SRF Project

Initiated on 12-06-2024 LS3C#5

CLOSED–
A6-01Identify and communicate to the LS3 Scientific Secretary the name of the speaker for the LS3 Readiness Review in SeptemberALL GROUPS/PROJECTS

Initiated on 26-06-2024 LS3C#6

CLOSED–
A7-01Inform Marine Gourber-Pace in case of operation or early commissioning that require accelerator and/or industrial control systems during LS3Experiments

Initiated on 03-07-2024 LS3C#7

OngoingLong term action
R7-01White Rabbit Central Timing components shall be tested by equipment owner before installation in particular before installation in SM18 and Linac4Equipement groups

Initiated on 03-07-2024 LS3C#7

OngoingLong term action
R7-02Anticipate a potential need for procurement contract extensions in case of a shift of the start of LS3All Groups/Projects

Initiated on 03-07-2024 LS3C#7

Ongoing–
R7-03Announce all requests to SCE-SAMAll Groups/Projects

Initiated on 03-07-2024 LS3C#7

Ongoing–
A8-01

To communicate the needs for additional dosimeters and training for LS3 to the RP service. S. Roesler (HSE-RP) will report on this subject in one of the upcoming LS3

All Groups/Projects

Initiated on 24-07-2024 LS3C#8

Ongoing

End June 2025
A9-01To verify the respective 171 PLAN contribution for which EN-EL misses a ticket request as well as the 34 SNOW tickets classified as incomplete tickets by EN-ELAll Groups/Projects

Initiated on 07-08-2024 LS3C#9

Ongoing–
R10-01Ensure proactive coordination and adapt schedule with service/equipment groups, facilities, and projects for interventions on the power network of critical and safety equipment during LS3EN/EL

Initiated on 21-08-2024 LS3C#10

OngoingIntegrated in EL quality plan
A10-01Communicate the impacts of the EN-EL consolidation activities on users and in particular experiments.EN/EL and ALL

Initiated on 21-08-2024 LS3C#10

CLOSEDCoordination meetings initiated
A10-02Review the invalidated PLAN contributions related to cable identification, as the YETS 2024-2025 is the final opportunity to address this.All Groups/Projects

Initiated on 21-08-2024 LS3C#10

Ongoing–
A10-03Review and finalize the ECRs for YETS 2024-2025.All Groups

Initiated on 21-08-2024 LS3C#10

Ongoing–
A10-04Review the ECRs for LS3 (i.e. check if anything is missing, incorrect, or incomplete).All Groups

Initiated on 21-08-2024 LS3C#10

Ongoing–
A10-05Review the integration studies/ECRs list to keep it as up to date as possible.All Groups/Projects

Initiated on 21-08-2024 LS3C#10

Ongoing–
A11-01Provide lists of pressure safety valves validations, AUG tests, smoke detection systems
tests, and other critical safety systems that need periodical tests (scope YETS 2025-26)
to LS3-scientific-secretary@cern.ch (then communicated to HSE)
All Groups

Initiated on 16-10-2024 LS3C#11

OngoingEnd of 2024
A12-01Finalization of Experimental Areas ECRs for YETS 2024-25All groups concernedInitiated on 30-10-2024 LS3C#12Ongoing–
A13-01Look at the list of facilities requesting to run during
LS3 and the respective requested services (including EN-EL). Raise any concerns/issues by mid-January 2025 to B.Mikulec or via the LS3 Scientific Secretary
All groups/services

Initiated on 27-11-2024 LS3C#13

Ongoing

Mid-January 2025

Deadline extended to end of March 2025

A14-01
Provide the name of the safety person(s) (if not part of
the LS3C members already) to be invited to the safety-dedicated LS3 meeting that will be held in May
2025.
Provide the name of the safety person(s) (if not part of
the LS3C members already) to be invited to the safety-dedicated LS3 meeting that will be held in May
2025.
ALL groups/projectsInitiated on 19-02-2025 LS3C#14Ongoing31st of March 2025.
Provide the name of the safety person(s) (if not part of
the LS3C members already) to be invited to the safety-dedicated LS3 meeting that will be held in May
2025.
A14-02Provide or update the space request needs according to the new LS3 schedule. Inform if barracks/bungalows are provided by Contractors or by CERN.ALL groups/projectsInitiated on 19-02-2025 LS3C#14Ongoing28th of February 2025
A14-03Submit all requests related to IT cabling (DC-IT) for the LS3 by SNOW ticket before the 31st of March 2025 and create the corresponding PLAN contribution (link the SNOW ticket number). Late requests may be subject to long delays or declined.ALL groups/projectsInitiated on 19-02-2025 LS3C#14Ongoing31st of March 2025
A14-04Record in the RW forecast share-point any equipment presently stored in storage buildings that will be disposed as radioactive waste.ALL groups/projectsInitiated on 19-02-2025 LS3C#14Ongoing30th of June 2025.

Task numbering according to its character:

<character><sessionNo.>-<occurrence>

Character A : ACTION

Character R : RECOMMENDATION

Character D : DECISION