Resolutions

List of Actions, Recommendations, Decisions

STATUSDOMAINTASK #TYPEDESCRIPTIONASSIGNEE/ RELATED_TODEADLINEOPENED INĀ 
OPENCoordination / ScheduleF42-01FOLLOW-UPCompatibility of AICE access system works in 2029 with PSS-CONS to be confirmed by EN-AA.LS3 Coordination2026-10-23 LS3C #42
OPENExperimentsA42-01ACTIONto provide feedback to LS3C by November 13th on their availability to work on the FASER, SND and AICE projects during LS3.Groups2026-10-23 LS3C #42
OPENEngineering / IntegrationA42-01ACTIONto review and comment the ECR for the Infrastructure preparation in UJ12 (including the move of the wall of TI12 behind FASER) during LS3: https://edms.cern.ch/document/3308480/0.1).Groups2026-10-23 LS3C #42
OPENExperimentsA42-02ACTIONto give feedback to the experiments and the LS3C chairs by 13th of November 2026 on resources availability for FASER and SND.Groups2026-10-23 LS3C #42
OPENExperimentsA42-03ACTIONto give feedback by 13th of November 2026 to the experiment and the LS3C chairs on resources availability for AICE.Groups2026-10-23 LS3C #42
OPENEngineering / IntegrationF40-01FOLLOW-UPPresent an update on status of Drawings and Installation NC at LS3C beginning 2027EN-ACE-INT2026-09-25 LS3C #40
OPENCoordination / ScheduleA40-01ACTIONPropose the strategy to IEFC to address the leaks issue on PSB quadrupolesTE-MSC2026-09-25 LS3C #40
OPENCoordination / ScheduleA40-02ACTIONPropose the strategy to manage the supports and girders in the Injectors ComplexEN-ACE206-09-25 LS3C #40
OPENCoordination / ScheduleA38-01ACTIONTo give a schedule status update to the LS3C in October 2026.BST team2026-08-26 LS3C #38
OPENSafetyA36-01ACTIONPresent the analysis of the sector 81 barrier incident and the lessons learntLS3 Safety Link Persons2026-07-29 LS3C #36
OPENCoordination / ScheduleA36-03ACTIONOpen Days status update presentation once the list of areas to be visited is definedOpen Days coordination2026-07-29 LS3C #36
OPENSafetyA36-07ACTIONEvaluate the HSE proposal and provide feedback by August 12thGroups/Projects2026-07-29 LS3C #36
OPENSafetyA36-08ACTIONReport decision on Processes for el. installations without C2E appointed yet at the LS3CHSE2026-07-29 LS3C #36
OPENExperimentsF35-03FOLLOW-UPTo send representatives to the weekly ATLAS coordination meetingsService groups2026-07-15 LS3C #35
OPENServices ELR34-01RECOMMENDATIONTo look at the connectors list and reach out to CSTSC in case of needs for LS3 (contacts: christophe.rabuffi@cern.ch or vito.vizziello@cern.ch) and in case of issues or concerns on connectors outside of the \href{https://indico.cern.ch/event/1684171/contributions/7150707/attachments/3306477/5916451/20260701_LS3C_CSTSC_ObsoleteConnectors_v1_2.pptxall groups and projects2026-07-01 LS3C #34
OPENControls & SoftwareF33-01FOLLOW-UPUpdate on the performance and user-friendly indicators and feedback from users on the ITM tool after the start of LS3 in LHC (September 2026)LS3 Coordination2026-092026-06-03 LS3C #33
OPENCoordination / ScheduleA33-01ACTIONFeedback from the Groups on ALADDIN to the LS3C. The feedback will be further shared with M. Brugger for the roadmap.All groups2026-06-03 LS3C #33
OPENCoordination / ScheduleF\_MC-01FOLLOW-UPSY LHC: critical follow-up items remain for: TCDS materials (HL-WP14), AC Dipole strategy, RF recommissioning, collimator reliability, MKI Cool (ABT).SY-STI2026-05-29 LS3C Checkup
OPENCoordination / ScheduleF\_MC-03FOLLOW-UPBST ReadinessTE-VSC2026-05-29 LS3C Checkup
OPENLogistics / RadioprotectionF\_MC-04FOLLOW-UPCoordination between RP OP, RP shipping and RPW. RP working time aligned with other teams (double/night shifts).NA-CONS Project2026-05-29 LS3C Checkup
OPENLogistics / RadioprotectionF\_MC-05FOLLOW-UPNeed for a derogation, especially for TCC2 (send RP material tagged as waste as soon as possible to the RWTC to avoid repeated handling and exposure in the storages/buffers).NA-CONS Project2026-05-29 LS3C Checkup
OPENLogistics / RadioprotectionF\_MC-06FOLLOW-UPStatus Rad-Hard Cables and Configuration to be modified (Patch Panels)EN-EL2026-05-29 LS3C Checkup
OPENControls & SoftwareF\_MC-10FOLLOW-UPGIS Rack Portal – Not updated.LS3 Coordination2026-05-29 LS3C Checkup
OPENCoordination / ScheduleF\_MC-11FOLLOW-UPLack of margin in the North Area schedule could directly lead to delays, and the planning should be closely monitored.NA-CONS Project2026-05-29 LS3C Checkup
OPENRadioprotection / SafetyF\_MC-13FOLLOW-UPStatus logistics : doses, availability of all necessary teams, feedback on CTD/IBDRS lessons learnedHSE-RP2026-05-29 LS3C Checkup
OPENCoordination / ScheduleF32-03FOLLOW-UPAICE Status update in August 2026 including PLAN revisions and the review of the compatibility with LHC planning in November 2026LS3 Coordination2026-08 PLAN2026-05-20 LS3C #32
OPENEngineeringF29-03FOLLOW-UPDefinition of connectors (and obsolescence) for the irradiated cables to be replacedLS3 Coordination / EN-EL / (HL Task Force for issue related to HL)2026-092026-03-25 LS3C #29
OPENControls & SoftwareF29-01FOLLOW-UPFeedback on the Workflow Management Tool and possible user extension for other equipments/groups activitiesLS3 Coordination2026-08 and Final 2026-122026-03-25 LS3C #29
OPENEngineering / IntegrationA25-03ACTIONUpdate Databases with the list of 495 circuits and new power converter names for SPS and Transfer LinesSY-EPC, BE-OP, EN-ACE-CL2026-06-302025-11-26 LS3C #25
SUSTAINEDRadioprotection / SafetyF32-02FOLLOW-UPTo minimise the number of persons above 3 mSv over 12 sliding months as per the LS3 safety objective.LS3 coordination and RPDashboards review2026-05-20 LS3C #32
SUSTAINEDLogistics / RadioprotectionR30-01RECOMMENDATIONSome shielding blocks are highly demanded and their use must be optimised.All Projects / BE-EA2026-092026-04-22 LS3C #30
SUSTAINEDEngineering / IntegrationR25-01RECOMMENDATIONIdentify and schedule all the necessary scans to be performed at the end of LS3ALL GROUPS/PROJECTSN/A2025-11-26 LS3C #25
SUSTAINEDRadioprotection / SafetyA17-04ACTIONProceed with the request of dosimeters needed for the whole LS3 period.All groupsN/A2025-05-14 LS3C #17
SUSTAINEDSafety / TrainingR17-01RECOMMENDATIONRequest for training by pre-booking as soon as possible (1 year to 6 months before)All groups / TrainingN/A2025-05-14 LS3C #17
SUSTAINEDEngineering / IntegrationA15-02ACTIONReview accelerators’ ECRs (LS3) and contact EN-ACE-CL for update.Groups’ configuration managers2025-06-302025-04-02 LS3C #15
SUSTAINEDInfrastructureR07-03RECOMMENDATIONAnticipate/announce as soon as possible all your requests to SCE-SAMAll groups/ projectsN/A2024-07-03 LS3C #7
SUSTAINEDEngineering / IntegrationR02-03RECOMMENDATIONEquipment drawings shall be released – “Valid for Production” or “Valid for Installation” – at the end of the design study or upgrade. Design OfficesN/A2024-04-17 LS3C #2

Task numbering schema:
<CHAR><SESSION_NO>-<OCCURENCE>
CHAR = A : ACTION
CHAR = R : RECOMMENDATION
CHAR = D : DECISION
CHAR = F : FOLLOW-UP