Resolution recently closed:
| STATUS | DOMAIN | TASK # | TYPE | DESCRIPTION | ASSIGNEE/ RELATED_TO | DEADLINE | OPENED IN | CLOSE COMMENTS |
| DECISION | Coordination / Schedule | D42-01 | DECISION | The SND core-drilling PLAN activity is cancelled. | 2026-10-23 LS3C #42 | |||
| DECISION | Logistics / Radioprotection | D41-01 | DECISION | BE EA and LS3 Coordination: The iron shielding from the CNGS hadron stopper will not be recovered during LS3. | 2026-10-09 LS3C #41 | |||
| DECISION | Coordination / Schedule | D39-01 | DECISION | New PLAN Activities/Contributions first addressed by PLAN coordinator and then status update announcement at the LS3C | 2026-09-09 LS3C #39 | |||
| CLOSED | Infrastructure | A39-01 | ACTION | To communicate the information regarding the planned shutdown of the central compressed-air production plant at the Meyrin site within their respective groups and to ensure that all installation owners, workshop supervisors and compressed-air users are informed. Report any incompatibility to EN-CV before 9~October 2026 (to A. Fournier and G. Petrika) | Groups and Projects | 2026-09-09 LS3C #39 | Can be closed > Follow up by CV on LS3C 6.11 | |
| CLOSED | Safety | A36-02 | ACTION | Recirculate the memo on appropriate work clothing during heatwaves | LS3 Coordination | 2026-07-29 LS3C #36 | ||
| CLOSED | Engineering | A36-04 | ACTION | Present the outcome of the ELQA at Warm measurement at the LS3C | TE-MPE | 2026-07-29 LS3C #36 | ||
| CLOSED | Engineering | A36-05 | ACTION | Present the outcome of the Leak Tests at Warm at the LS3C | TE-VSC | 2026-07-29 LS3C #36 | ||
| CLOSED | Safety | A36-06 | ACTION | Present the deployment of ESP in the Injectors at the LS3C | ESP | 2026-07-29 LS3C #36 | Refer to presentation of S. Evrard An ESP update will be provided at the next LS3 event in May 2027 | |
| CLOSED | Engineering | F35-02 | FOLLOW-UP | Investigation on the “Socket Breakers” trip (Power Converter LHC-4 RF tests) | LS3 Coordination | 2026-07-15 LS3C #35 | Closed by SY DSO 2026-08-13 No incident or safety issue identified | |
| CLOSED | Services Alarms | F35-04 | FOLLOW-UP | Location of the SAREP alarm transmission system rack in the ISOLDE Hall | LS3 coordination | 2026-07-15 LS3C #35 | Miriam MUNOZ CODOCEO from EN-AA contacted Following a review with EN-AA as the equipment responsible, the racks will remain at their current location in the ISOLDE hall because relocation would be complex and no upgrade is planned that would provide an opportunity to transfer this critical system. | |
| CLOSED | Coordination / Schedule | D35-01 | DECISION | Document: “Running facilities in LS3” – EDMS No.3463172 V0.2->V1.0 approved with caveat (also to be approval at IEFC). Caveat addressed in further updates. | 2026-07-15 LS3C #35 | |||
| CLOSED | Coordination / Schedule | F35-01 | FOLLOW-UP | AET additional requests/measures | LS3 coordination | 2026-07-15 LS3C #35 | Follow-up on LS3 coord. à CLOSED | |
| CLOSED | Infrastructure | A34-01 | ACTION | To inform SCE if specific areas should be included in the round of guards. | all groups/projects | 2026-07-01 LS3C #34 | If no feedback from Mauro, we close it and announce it at LS3C just to retrigger request | |
| CLOSED | Coordination / Schedule | A34-02 | ACTION | Status PLAN ID 14498, 14499 and 14500. | LS3 PLAN officers | 2026-07-01 LS3C #34 | These activities are being followed up by the PLAN Offices (EN-ACE): 14498 is already approved. 14499 and 14500 are awaiting a contribution validation from EN-THE | |
| CLOSED | Coordination / Schedule | F\_MC-02 | FOLLOW-UP | Go/No-Go awaited on the 10MHz (awaiting ITS in June 2026) | LS3-Coordination | 2026-05-29 LS3C Checkup | Presented at IEFC by RF | |
| CLOSED | Logistics / Radioprotection | F\_MC-07 | FOLLOW-UP | Shielding – Lack of resources in EA (coordination) and THE (transport) – 5 FTE.years Industrial support are missing | BE-EA | 2026-05-29 LS3C Checkup | To close, referring to report by Sebatsien on shielding blocks (Resources are available)-Normally in the minutes | |
| CLOSED | Experiments | F\_MC-08 | FOLLOW-UP | Services for experiments running during LS3 | LS3 Coordination | 2026-05-29 LS3C Checkup | https://edms.cern.ch/document/3463172/1.0 | |
| CLOSED | Infrastructure | F\_MC-09 | FOLLOW-UP | Status NA Chillers | EN-CV | 2026-05-29 LS3C Checkup | Being followed up by LS3 Coordination Team | |
| CLOSED | Radioprotection / Safety | F\_MC-12 | FOLLOW-UP | Procedure on what to do in case of significant increase of collective and individual dose with respect to values approved by the ALARA committee. | HSE-RP | 2026-05-29 LS3C Checkup | S. ROESLER – Update on radiation dose alerts and approval processes | |
| CLOSED | Coordination / Schedule | F32-01 | FOLLOW-UP | Deployment of the new “Autorisation Exceptionnelle de Travail” workflow | LS3 Coordination | 2026-07-01 | 2026-05-20 LS3C #32 | Feedback expected deployment on the 2026-07-01 |
| CLOSED | Coordination / Schedule | F31-01 | FOLLOW-UP | Optimization of TE resources assigned to HL-LHC WP6A (including a report on issues arising in the meantime) and refurbishment of the HIE-ISOLDE cryomodule (CM), with a decision point on the CM1 refurbishment by September 2026. | LS3 Coordination | update 2026-09 | 2026-05-06 LS3C #31 | Update and decision (if needed) on Sep’26 |
| CLOSED | Safety | F30-03 | FOLLOW-UP | ESP status at the start of LS3. | LS3 Coordination | 2026-08 | 2026-04-22 LS3C #30 | An ESP update will be provided at the next LS3 event in May 2027 |
| CLOSED | Safety | F30-02 | FOLLOW-UP | ESP: Anticipation of the release by HSE of the roles and responsibilities document, originally targeted for June 2026. | HSE / ESP | 2026-06-03 | 2026-04-22 LS3C #30 | No anticipation of the release |
| CLOSED | Safety | A25-01 | ACTION | ESP: Groups should designate a data officer responsible for cleaning and maintaining electrical information in the databases | CEM, EA, GM, AA, CV, HE, EL, ABT, BI, RF, EPC, STI, CRG, VSC, MPE | 2026-07-01 | 2025-11-26 LS3C #25 | is being reviewed within the ATS Digital Thread Panel |
| CLOSED | Infrastructure | R22-02 | RECOMMENDATION | To contact the SCE-SAM LS3 contact persons to complete the information on PLAN on the topic of civil engineering to be installed during LS3. | ALL | 2026-11-30 | 2025-08-20 LS3C #20 | Each requester now has a dedicated contact who can follow up and support the processing of their request. A contact person has been provided by SCE for all new LS3 requests for each experimental area/complex. |
Resolution closed at (or before) 2026-06-03 LS3 Committee #33
| STATUS | DOMAIN | TASK # | TYPE | DESCRIPTION | ASSIGNEE | DEADLINE | OPENED IN | CLOSE COMMENTS |
| DECISION | Safety | D26-02 | DECISION | SPS LSS2: EN-EL is responsible for all necessary lockout procedures required for the removal and installation of cables | SPS LSS2 Coordination | N/A | 2026-01-14 LS3C #26 | No comment from the committee |
| DECISION | Coordination and Schedule | D26-01 | DECISION | LS3 Committee endorses the mandate of the technical coordinator of the SPS LSS2 activities according to the document EDMS No.3390182 | SPS LSS2 Coordination | N/A | 2026-01-14 LS3C #26 | No comment from the committee |
| DECISION | Coordination and Schedule | D18-01 | DECISION | Any new PLAN activity requests must first be presented and appropriately justified at the LS3 Committee meetings. | All | Until new PLAN version | 2025-05-28 LS3C #18 | No comment from the committee |
| DECISION | Logistics | D16-01 | DECISION | All new space requests must first be presented and appropriately justified either at the LS3 Committee meetings or during ad-hoc meetings. | All | N/A | 2025-04-30 LS3C #16 | No comment from the committee |
| CLOSED | Radioprotection / Safety | R27-01 | FOLLOW-UP | The RSOs (RSSOs) should, proactively, be in regular contact with the DIMR owners of (possible) L3 interventions | All groups/ projects | N/A | 2026-01-14 LS3C #27 | Closed at the LS3 Mission 2026-05-28 |
| CLOSED | Infrastructure | R20-01 | RECOMMENDATION | Organise preventive maintenance before LS3 on the building automatic doors for material, to reduce workload during LS3. | Projects and Experiments | 2026-06-30 | 2025-06-25 LS3C #20 | No feedback from the committee |
| CLOSED | Radioprotection | R07-04 | RECOMMENDATION | Contact N. QUINQUIS in case of needs relative to logistical and dismantling operations in controlled radiation areas during LS3. | All groups/ projects | N/A | 2024-07-03 LS3C #7 | No others major requests expected, any new request shall be addressed individually |
| CLOSED | Radioprotection / Logistics | R02-02 | RECOMMENDATION | The need for transports of bulky and/or highly activated objects or activated items with exotic material composition (e.g. heavy metals) should be announced to RP and EN-HE as soon as possible. | Radioactive transports | N/A | 2024-04-17 LS3C #2 | Transports of bulky and/or highly activated objects identified |
| CLOSED | Engineering&Integration | R02-01 | RECOMMENDATION | Relevant Projects and Groups must have representatives at the ICL Meetings. | All groups/ projects | N/A | 2024-04-17 LS3C #2 | Groups and projects are represented at ICL Meetings |
| CLOSED | Radioprotection / Logistics | F29-02 | FOLLOW-UP | Strategy of temporary storage of radioactive equipment (ABT) | SPS LSS2 Coordination | 2026-04-22 / 2026-05-31 | 2026-03-25 LS3C #29 | Strategy has been presented during LSS2 coordination kick off meeting and during LS3 event, no particular negative feedback or opposition. |
| CLOSED | Radioprotection / Logistics | A28-04 | ACTION | Organise an add-hoc discussion on NA-CONS RW | LS3 coordination, RP and NA-CONS | 2026-06-30 | 2026-02-25 LS3C #28 | Issue managed by the Task Force – Thomas Zickler |
| CLOSED | Radioprotection / Logistics | A28-03 | ACTION | Analyse the RW forecast data related to the peak in Q3-2026 | LS3 Coordination | 2026-05-06 | 2026-02-25 LS3C #28 | Issue managed by the Task Force Radioactive Storage – Germana Riddone (EDMS#3447180) |
| CLOSED | Radioprotection / Logistics | A28-02 | ACTION | Provide RW forecast data related to the peak in Q3-2026, split by location, group/project | RP-RWM | 2026-05-06 | 2026-02-25 LS3C #28 | https://edms.cern.ch/document/3447180 |
| CLOSED | Logistics | A27-01 | ACTION | Identification of components to be moved from Building 954/955/879 | RP/Space Management team | Closed 2026-02-25 LS3C #28 | 2026-01-14 LS3C #27 | Managed by Space Management Task Force |
| CLOSED | Coordination and Schedule | A26-01 | ACTION | Verify or request the contributions of BI/VSC/ABT/…, particularly regarding the potential need to dismantle equipment for the cabling campaign | SPS LSS2 Coordination | 2026-03-25 | 2026-01-14 LS3C #26 | Contribitions checked and clarified |
| CLOSED | Engineering&Integration | A25-02 | ACTION | Release the new naming convention SPS-PM-QA-0001 EDMS No.3384371 | SPS and Transfer Lines stakeholders | Closed 2026-03-25 LS3C #29 | 2025-11-26 LS3C #25 | https://edms.cern.ch/document/3384371 |
| CLOSED | Safety | A22-01 | ACTION | LAACS/LASS access numbers shall be updated. | EN-AA | Closed 2026-03-25 LS3C #29 | 2025-08-20 LS3C #20 | Information given to EN-AA for updating the systems: https://adams-intranet.web.cern.ch/peopleinzones.php?where=LHC |
| CLOSED | Coordination and Schedule | A19-02 | ACTION | Validate the Assumptions for LS3 schedule LHC-PM-MS-0022 optimisation Slides 8 | LS3 Coordination | 2026-05-06 | 2025-06-11 LS3C #19 | Last assumption “Collimator dismantling during warm-up” confirmed at LS3 Mission |
| CLOSED | Safety | A17-01 | ACTION | Document defining roles and responsibilities of the WSS. | EN-DSO/HSE | 2026-02-25 | 2025-05-14 LS3C #17 | https://edms.cern.ch/document/3440507 https://edms.cern.ch/document/3436963 |
| MERGED with F31-01 | Coordination and Schedule | A30-01 | ACTION | Provide an update in September 2026 about the progress of HIE ISOLDE CM1 refurbishment vs WP6a activities. | TE | 2026-09 | 2026-04-22 LS3C #30 | Merge with F31-01 No reported at Committee #33 |
| MERGED with F31-01 | Coordination and Schedule | A31-01 | ACTION | Review the HIE-ISOLDE PLAN activities 14157 and 14158 by 31st of July 2026. | BE-OP and SY-RF | 2026-07-31 | 2026-05-06 LS3C #31 | |
| CLOSED | LS3 Committee | A28-01 | ACTION | Identify departments link persons for the “Mission: LS3 checkup” event | TE, BE, EN, SY, SCE and IT department heads | 2026-04-01 | 2026-02-25 LS3C #28 | No reported at Committee #33 |
| MERGED with A15-02 | Engineering&Integration | A10-05 | ACTION | Review the integration studies/ECRs list to keep it as up to date as possible. | All groups/ projects | N/A | 2024-08-21 LS3C #10 |
Resolutions closed before the 2025-07-09 LS3C #21:
| TASK # | DESCRIPTION | ASSIGNEE | DEADLINE | DOMAIN | STATUS | OPENED IN | CLOSED IN |
| A2-01 | The activities to be scheduled during the LS3 involving EN-EL for major (de)cabling (i.e. HL-LHC, NA-CONS, PSS-CONS) should be requested at latest on 30th of June 2024. For all other projects and works the deadline is set to 30th of September 2024 | All groups/ projects | N/A | EN/EL | CLOSED | 2024-04-17 LS3C #2 | 2024-07-09 LS3C #21 |
| R7-02 | Anticipate a potential need for (procurement) contract extensions in case of a shift of the start of LS3 | All groups/ projects | N/A | Coordination and Schedule | CLOSED | 2024-07-03 LS3C #7 | 2024-07-09 LS3C #21 |
| A8-01 | To communicate the needs for additional dosimeters and training for LS3 to the dosimetry RP service. S. Roesler (HSE-RP) will report on this subject in one of the upcoming LS3 | All groups/ experiments | N/A | Radioprotection | OBSOLETE | 2024-07-24 LS3C #8 | replaced |
| A10-04 | Review the ECRs for LS3 (i.e. check if anything is missing, incorrect, or incomplete) | All groups | N/A | ECR and Integration | OBSOLETE | 2024-08-21 LS3C #10 | 2024-07-09 LS3C #21 |
| A14-01 | Provide the name of the safety person(s) (if not part of the LS3C members already) to be invited to the safety-dedicated LS3 meeting that will be held in May 2025, before the 31st of March 2025. | ALL groups/ projects | 2025-03-31 | Safety coordination | CLOSED | 2025-02-19 LS3C #14 | 2025-04-02 LS3C #15 |
| A14-02 | Provide or update the space request needs according to the new LS3 schedule. Inform if barracks/bungalows are provided by Contractors or by CERN. Before the 28th of February 2025. | ALL groups/ projects | 2025-02-28 | Space Management | CLOSED | 2025-02-19 LS3C #14 | 2025-04-02 LS3C #15 |
| A14-03 | Submit all requests related to IT cabling (DC-IT) for the LS3 by SNOW ticket before the 31st of March 2025 and create the corresponding PLAN contribution (link the SNOW ticket number). Late requests may be subject to long delays or declined. | All groups/ projects | 2025-03-31 | Infrasctructure | CLOSED | 2025-02-19 LS3C #14 | 2025-04-02 LS3C #15 |
| A15-03 | Plan a presentation in a LS3 Committee summer 2025 meeting on the update of the ECRs and integration status. | LS3 Scientific secretaries | 2025-07-31 | LS3 Committee | CLOSED | 2025-04-02 LS3C #15 | 2025-07-09 LS3C #21 |
| A9-01 | To verify the respective 171 PLAN contribution for which EN-EL misses a ticket request as well as the 34 SNOW tickets classified as incomplete tickets by EN-EL | All groups/ projects | N/A | EN/EL | CLOSED | 2024-08-07 LS3C #9 | 2024-07-09 LS3C #21 |
| A10-02 | Review the invalidated PLAN contributions related to cable identification, as the YETS 2024-2025 is the final opportunity to address this. | All groups/ projects | N/A | YETS2024-2025 | CLOSED | 2024-08-21 LS3C #10 | 2024-07-09 LS3C #21 |
| A10-03 | Review and finalize the ECRs for YETS 2024-2025. | All groups | N/A | YETS2024-2025 | CLOSED | 2024-08-21 LS3C #10 | 2024-07-09 LS3C #21 |
| A12-01 | Finalization of Experimental Areas ECRs for the YETS 2024-2025 | All groups concerned | N/A | YETS2024-2025 | CLOSED | 2024-10-30 LS3C #12 | 2024-07-09 LS3C #21 |
| A13-01 | Check list of facilities requesting to run during LS3 and respective requested services (including EN-EL). Raise any concerns/issues by mid-January to B.Mikulec or via the LS3 Scientific Secretary. | All services/ groups | 2025-04-15 | Running Facilities | CLOSED | 2024-10-27 LS3C #13 | Replaced by #16 |
| A14-04 | Record in the RW forecast share-point any equipment presently stored in storage buildings that will be disposed as radioactive waste. The deadline is set for 30th of June 2025. | All groups/ projects | 2025-06-30 | Radioprotection | CLOSED | 2024-02-19 LS3C #14 | 2024-07-09 LS3C #21 |
Resolutions closed before the 2024-11-27 LS3C #13 actions review:
| TASK # | DESCRIPTION | ASSIGNEE | DEADLINE | DOMAIN | STATUS | OPENED IN | CLOSED IN |
| A3-01 | To reach out to their RSO and inform RP regarding their planned interventions during LS3 before mid-June 2025, to assess if any ALARA Level 3 committee will be necessary | ALL GROUPS/PROJECTS | 2025-06-15 | Radioprotection | CLOSED | 2024-04-17 LS3C #3 | 2024-11-27 LS3C #13 |
| A4-01 | Reporting about L3 intervention at the LS3C within 6 weeks REMINDER: “each project leader needs to contact their RSO and each RSO needs to contact the groups in their department to collect the relevant information. | RP | 2024-07-15 | Radioprotection | CLOSED | 2024-05-29 LS3C #4 | 2024-11-27 LS3C #13 |
| A5-01 | Report on the power consumption simulations of SM18 during the reduction of the available electrical power capacity during LS3 | EN-EL | 2024-11-27 | EN/EL | CLOSED | 2024-06-12 LS3C #5 | 2024-11-27 LS3C #13 |
| R5-01 | Nominate a safety coordinator during the conception phase (part-time) | SRF Project | 2024-11-27 | Safety coordination / HSE | CLOSED | 2024-06-12 LS3C #5 | 2024-11-27 LS3C #13 |
| A6-01 | Identify and communicate to the LS3 Scientific Secretary the name of the speaker for the LS3 Readiness Review in September | ALL GROUPS | 2024-11-27 | LS3C events | CLOSED | 2024-06-26 LS3C #6 | 2024-11-27 LS3C #13 |
| A10-01 | Communicate the impacts of the EN-EL consolidation activities on users and in particular experiments. | EN-EL and ALL | 2024-11-27 | EN/EL | CLOSED | 2024-08-21 LS3C #10 | 2024-11-27 LS3C #13 Coordination meetings initiated |
| A10-06 | Check the LS3 Readiness Review agenda before 05th of September 2024 and report any feedback to the LS3 Scientific Secretary. | Groups/ Projects | 2024-11-27 | LS3C events | CLOSED | 2024-08-21 LS3C #10 | 2024-11-27 LS3C #13 |
| R10-01 | Ensure proactive coordination and adapt schedule with service/equipment groups, facilities, and projects for interventions on the power network of critical and safety equipment during LS3. | EN-EL | 2024-11-27 | EN/EL | CLOSED | 2024-08-21 LS3C # | 2024-11-27 LS3C #13 Integrated in EL quality plan |
| A14-01 | Provide the name of the safety person(s) (if not part of the LS3C members already) to be invited to the safety-dedicated LS3 meeting that will be held in May 2025, before the 31st of March 2025. | ALL groups/ projects | 2025-03-31 | Safety coordination | CLOSED | 2025-02-19 LS3C #14 | 2025-04-02 LS3C #15 |
| A14-02 | Provide or update the space request needs according to the new LS3 schedule. Inform if barracks/bungalows are provided by Contractors or by CERN. Before the 28th of February 2025. | ALL groups/ projects | 2025-02-28 | Space Management | CLOSED | 2025-02-19 LS3C #14 | 2025-04-02 LS3C #15 |
| A14-03 | Submit all requests related to IT cabling (DC-IT) for the LS3 by SNOW ticket before the 31st of March 2025 and create the corresponding PLAN contribution (link the SNOW ticket number). Late requests may be subject to long delays or declined. | All groups/ projects | 2025-03-31 | Infrasctructure | CLOSED | 2025-02-19 LS3C #14 | 2025-04-02 LS3C #15 |